Liphook Village Centre Road works:  July – September 2013

The programmed dates for the footway, kerbing and drainage works are as follows. NB: Businesses will operate as usual, including Clarke Gammon Wellers.


• Phase 1 - Headley Road (London Road for 30m) - closed from 29 July to 6 August
• Phase 2 - Haslemere Road (Portsmouth Road to Chiltee Manor) -closed from 12 August to 17 August
• Phase 3 - Liphook Square (London Road to Portsmouth Road) – closed from 7 August to 11
August including Saturday and Sunday
• Phase 4 - Midhurst Road (Junction Haslemere Road to Shipley Court) – closed from 19 August to 30 August
• Phase 5 - Portsmouth Road (Haslemere Road to Larch Close) – closed from 31 August to 13
September

In addition, resurfacing works will begin in September, and the following programmed dates are as follows:

• On 6 September, night working from 19:00hrs to 07:00 hrs on Liphook Square and Portsmouth Road, which involves closing Liphook Square, Portsmouth Road and Haslemere Road to the junction with Midhurst Road.
• On Saturday 7 September from 07:00hrs to 19:00hrs, Liphook Square and Portsmouth Road, same closures as above on Friday night
• On Sunday 8 September from 07:00hrs to 19:00hrs, Longmoor Road, Headley Road and London Road, which includes closing all the above for 30m apart from London Road which will be to Childerstone Close.
• On 14 & 15 September from 07:00hrs to 19:00hrs, Haslemere Road and Midhurst Road, which involves closing Haslemere to Chiltee Manor and Midhurst Road to Shipley Court.